Commission Delegated Regulation (EU) 2023/1184 sets out when electricity used to make hydrogen counts as fully renewable, and which test applies depends on the route. A direct line to the generator is Article 3. Grid-taken electricity has four routes under Article 4, and they are not equally demanding: a bidding zone above 90 per cent renewable in the previous calendar year needs none of the three conditions below, subject to a cap on hours; a bidding zone below 18 gCO2eq per MJ needs a power purchase agreement plus temporal and geographic correlation but not additionality; electricity taken during downward redispatch is treated separately; and everything else falls to the residual route where all three apply. A project siting in a Nordic zone is answering a different question from one siting in India, and holding renewable certificates satisfies none of the three on any route.
Additionality. The renewable installation has to have come into operation no more than 36 months before the hydrogen installation, and it should not have received operating or investment aid unless that support was repaid in full. Support for land, and support for a grid connection, do not disqualify. There is a transitional provision that a large share of current project timelines rests on, and it is routinely described wrongly: a hydrogen production installation coming into operation before 1 January 2028 is relieved of the 36-month test and the aid test until 1 January 2038. That is a fixed date, not a rolling ten years from each plant's own commissioning, so a plant starting in 2026 gets about eleven and a half years and one starting in 2024 got more. It does not extend to capacity added after 1 January 2028, which matters for a phased build. And it relieves only those two tests: the producer still has to own equivalent renewable generation or hold power purchase agreements covering at least the volume claimed, and temporal and geographic correlation are untouched by it.
Temporal correlation. Until 31 December 2029, hydrogen has to be produced in the same calendar month as the renewable generation matched to it. From 1 January 2030 the matching period becomes one hour. A Member State may bring the hourly rule forward to 1 July 2027 by notifying the Commission, so the applicable date is not the same across the EU. There is also a price-linked route: production during periods when the market clearing price in the relevant bidding zone is at or below EUR 20 per MWh, or below 36 per cent of the emission allowance price, is treated as satisfying the correlation.
Hourly matching changes what a plant's output is. If eligible renewable electricity exists for ten hours of a twenty-four hour run, the hydrogen attributable to those ten hours is RFNBO and the remainder is not. An annual renewable percentage cannot produce that split and a monthly one will not either, once the rule turns over.
Geographic correlation. Generation and consumption have to sit in the same bidding zone, or in zones connected in a way the regulation recognises. This is the condition Indian export projects find hardest, because the Indian grid does not map onto EU bidding-zone logic and long-distance deliverability is difficult to evidence. Co-location or a direct line removes most of the argument before it starts.